New Mexico Register / Volume XXIX,
Issue 7 / April 10, 2018
This is an
amendment to 14.5.3 NMAC, Section 9, effective 5/15/2018.
14.5.3.9 INSPECTIONS: The following inspections are required unless
otherwise indicated.
A. For work subject to the NMCBC.
(1) Footing and foundation inspection, see Section
110 of the IBC.
(2) Concrete slab or under floor
inspection, see Section 110 of the IBC.
(3) Lowest floor elevation, see Section 110 of the IBC.
(4) Frame inspection, see Section 110 of the IBC.
(5) Roof assembly inspection.
(6) Exterior
wall opening flashings.
(7) Weather resistive barrier inspection
is to be made after installation of the appropriate weather resistive barrier
and before such barrier is covered.
(8) Lath
and gypsum board, see Section 110 of the IBC.
(9) Fire
and smoke-resistant penetrations, see Section 110 of the IBC.
(10) Energy
efficiency inspection, see Section 110 of the IBC.
(11) Other
inspections required by the AHJ building official, see Section 110 of the IBC.
(12) Special
inspections, see Section 110 of the IBC.
(13) Final inspection, see Section 110 of the IBC.
B. For work subject to the NMRBC.
(1) Footing and foundation inspection,
see Section 109.1.1 of the IRC.
(2) Concrete
slab or under floor inspection, see Section 109 of the IRC.
(3) Frame and masonry inspections, see
Section 109.1.4 of the IRC.
(4) Roof
assembly inspection.
(5) Exterior
wall opening flashings.
(6) Weather resistive barrier inspection
is to be made after installation of the appropriate weather resistive barrier
and before such barrier is covered.
(7) Energy efficiency inspections and state of New Mexico
thermal bypass inspection checklist verification.
(8) Lath and gypsum board, see Section 109.1.5 of the IRC.
(9) Other
inspections required by the AHJ, see Section 109 of the IRC.
(10) Fire resistance rated construction
inspection, see Section 109.1.5.1 of the IRC.
(11) Final inspection, see Section 109.1.6
of the IRC.
C. For work subject to the NMEC.
(1) Temporary pole (if applicable).
(2) Underground or under-slab (if applicable).
(3) Rough-in:
(a) on residential projects, all wiring must be installed and
connections made-up;
(b) on commercial projects, perform inspections as required.
(4) Pre-final (if applicable).
(5) Final (electrical system is complete and energized).
D. For work subject to the NMMC.
(1) Rough inspection of all mechanical
work covered by permit after work has been installed and before it is covered
or concealed.
(2) Temporary heat (if applicable).
(3) Final inspection after all mechanical
work covered by permit has been installed and covered and after fixtures and
appliances have been attached.
(4) Operation of mechanical equipment
installed to replace existing equipment or fixtures. See the existing installations section
[116.2] of the currently adopted UMC.
E. For work subject to the NMPC.
(1) Rough inspection of all plumbing work
covered by permit after work has been installed and before it is covered or
concealed.
(2) Top-out inspection of all vented
piping above floor and all extensions through the roof and walls. The top-out testing procedures are at the
option of the inspector to insure the system is free from leaks or defects.
(3) Water distribution including all
water piping inside and under a building.
(4) Water service piping from a service
meter to a connection outside the building.
(5) Final inspection after all plumbing
work covered by permit has been installed and covered and after fixtures and
appliances have been attached.
(6) Operation of plumbing equipment to
replace existing equipment or fixtures, see the existing installations section
[103.5.2] of the currently adopted UPC.
F. Additional inspections. In addition to required inspections, the AHJ
or CBO is authorized to make or require other inspections of any construction
work to ascertain compliance with the provisions of the applicable New Mexico
construction codes.
G. Re-inspections.
(1) A re-inspection fee shall be permitted to be assessed for each
inspection or re-inspection when such portion of work for which an inspection
is called and is not complete or when the required corrections have not been
made. This provision shall not to be
interpreted as requiring a re-inspection fee the first time work is rejected
for failure to comply with the applicable New Mexico construction codes, but
for controlling the practice of requesting inspections before the work is ready
for inspection or re-inspection. No
additional inspections of the work will be performed until the required fees
have been paid and re-inspection has been made.
(2) Re-inspection
fees may be assessed when the approved plans are not readily available to the
inspector, or for deviating from plans without the approval of the authority
having jurisdiction.
(3) Re-inspection
fees may be assessed for failure to provide access on the date for which the
inspection is requested.
[14.5.3.9 NMAC - Rp,
14.5.3.9 NMAC, 11/15/2016; A, 5/15/2018]