New Mexico Register / Volume XXIX,
Issue 12 / June 26, 2018
This is an
amendment to 19.15.14 NMAC, amending Sections 1 and 8, effective 6/26/2018.
19.15.14.1 ISSUING AGENCY: [Energy, Minerals and Natural Resources
Department, Oil Conservation Division] Oil Conservation Commission.
[19.15.14.1
NMAC - N, 12/1/2008; A, 6/26/2018]
19.15.14.8 PERMIT TO DRILL, DEEPEN OR PLUG
BACK:
A. Permit required. An operator is required to
obtain a permit approved by the division prior to commencing drilling,
deepening or re-entry operations, commencing an additional lateral, plugging a
well back to a different pool, or completing or re-completing a well in an
additional pool.
B. [Mineral
owner or lessee consent required. An
operator shall not file an application for permit to drill nor commence
drilling operations until the operator has either:
(1) received the
consent of at least one lessee or owner of an unleased mineral interest at the
proposed bottom hole location; or
(2) obtained a
compulsory pooling order from the division.
In addition, an operator filing an application for permit to drill for a
horizontal or directional well shall comply with Subsection A of 19.15.16.15
NMAC.] Mineral owner or
working interest owner consent required.
(1) An
operator shall not file an application for permit to drill nor commence
drilling operations until the operator has either:
(a) received the consent of at least one working interest owner
or owner of an unleased mineral interest at the proposed bottom hole location;
or
(b) obtained a compulsory pooling order from the division.
(2) In
addition, an operator filing an application for permit to drill a horizontal
well shall comply with Paragraph (1) of Subsection A of 19.15.16.15 NMAC.
[19.15.14.8
NMAC - Rp, 19.15.3.102 NMAC, 12/1/2008; A, 2/15/2012;
A, 4/16/2012; A, 6/26/2018]