TITLE 18 TRANSPORTATION
AND HIGHWAYS
CHAPTER 27 HIGHWAY CONSTRUCTION GENERAL PROVISIONS
PART 5 CONTRACTOR PREQUALIFICATION RULE
18.27.5.1 ISSUING AGENCY:
The
New Mexico Department of Transportation, PO Box 1149, Santa Fe, New Mexico,
87504-1149.
[18.27.5.1
NMAC - Rp, 18.27.5.1 NMAC, 1/1/2015]
18.27.5.2 SCOPE: This rule
applies to the New Mexico department of transportation construction projects
and to all contractors and subcontractors seeking or anticipating the
performance of work within the project limits.
[18.27.5.2
NMAC - Rp, 18.27.5.2 NMAC, 1/1/2015]
18.27.5.3 STATUTORY AUTHORITY:
Section
13-1-82 NMSA 1978 (1984, as amended through 2012) and Section 13-1-133 to -134
NMSA 1978 (1984, as amended through 2012) Sections 67-3-2 (2003), 67-3-11
(2003), 67-3-14 (2003), and 67-3-43 (1983) NMSA 1978, 23 USC Section 112(b), 23
CFR Sections 635.110 and 635.114.
[18.27.5.3
NMAC - Rp, 18.27.5.3 NMAC, 1/1/2015; A, 1/1/2019]
18.27.5.4 DURATION: Permanent.
[18.27.5.4
NMAC - Rp, 18.27.5.4 NMAC, 1/1/2015]
18.27.5.5 EFFECTIVE DATE:
January
1, 2015, unless a later date is cited at the end of a section.
[18.27.5.5
NMAC - Rp, 18.27.5.5 NMAC, 1/1/2015]
18.27.5.6 OBJECTIVE: To establish
policies and procedures for a determination of responsibility through a
contractor prequalification system that directly rewards good performers and
encourages poor performers to improve.
[18.27.5.6
NMAC - Rp, 18.27.5.6 NMAC, 1/1/2015]
18.27.5.7 DEFINITIONS:
A. This rule adopts the
abbreviations, symbols and definitions in the division 100-general provisions
of the New Mexico department of transportation current edition of the standard
specifications for highway and bridge construction and incorporates the same by
reference.
B. CID is the
abbreviation of construction industries division.
C. Compass form
means the New Mexico department of transportation form generated at project closure
that documents certain contractor performance measurement data.
D. Innovative
contracting is an alternate form of competitive bidding consistent with federal
and state procurement laws that can result in work being awarded to a
responsible bidder that may not submit the lowest monetary bid.
E. Modified bid
amount means the contractor’s bid multiplied by the contractor’s
prequalification factor rolling average or Pqfra. The modified bid amount will be used solely for
determining the apparent lowest responsible bidder. The modified bid amount
will not be used for payment.
F. Packet means the
current New Mexico department of transportation contractor prequalification application
from the office of inspector general.
G. Performance
factor or Pf means the numerical quantification of a contractor’s past
performance on closed projects for certain objectively measureable criteria.
H. Pf claim or Pfc means
the performance measurement of a contractor’s unsuccessful demand for
reconsideration seeking additional compensation or contract time beyond the
cabinet secretary administrative remedy level.
I. Pf disincentive
or Pfd means the performance measurement of a contractor’s quality of work
related to certain contract items. Applicable
contract items for disincentive are the following sections 401 pavement
smoothness measurement, 403 open graded friction course, 403 - a warm mix
asphalt - open graded friction course, 404 rubberized open graded friction
course, 416 minor paving, 417 miscellaneous paving, 423 hot mix asphalt - major
paving, 424 warm mix asphalt - major paving, 450 major portland cement concrete
pavement, 451 minor portland cement concrete pavement, 456 continuously
reinforced concrete pavement, and division 900 quality criteria.
J. Pf liquidated
damages or Pfld means the performance measurement of a contractor’s timely
completion of the contract.
K. Pf
non-conformance or Pfn means the performance measurement of a contractor’s
compliance with the terms and conditions of the contract.
L. Pf safety or Pfs
means the performance measurement of a contractor’s safety reflected by the
contractor’s experience modifier rate or emr provided by the contractor’s
bonding company.
M. Pf subcontractor or
Pfsc means the performance measurement of a contractor’s prompt payment of its first
tier subcontractors.
N. Pqf rolling
average or Pqfra means the final measure of responsibility that is applied to
the contractor’s bid resulting in the modified bid amount.
O. Prequalification
factor year or Pqfyr means the yearly calculation of a contractor’s performance
factors.
P. Prequalification
factor or Pqf means the overall mathematical analysis of the performance
factors that measures contractor responsibility. Prequalification factor is
abbreviated Pqf.
Q. Prequalification
packet means the New Mexico department of transportation form submitted
annually.
R. Project closure
means completion of the project and occurs on the date that the state
construction engineer or New Mexico department of transportation designee signs
the compass form.
S. Responsibility
means an objective determination based on past performance by the New Mexico
department of transportation of the contractor’s capability in all respects to
perform fully and make satisfactory delivery the requirements of the contract
including the integrity and reliability that will assure good faith
performance.
T. Rolling average
means a calculation to analyze data points by creating a series of averages of
different subsets of the full data set.
[18.27.5.7
NMAC - Rp, 18.27.5.7 NMAC, 1/1/2015; A, 1/1/2019]
18.27.5.8 PREQUALIFICATION PROCEDURE: The most current version of the prequalification
packet to obtain prequalified status must be obtained from the office of
inspector general of the New Mexico department of transportation website. Each contractor and subcontractor seeking to
become prequalified shall submit the prequalification packet and any supporting
information to the New Mexico department of transportation office of inspector
general as indicated in the prequalification packet. Deadlines are calculated from the date office
of inspector general receives the new or renewal packet. Requests for prequalification will not be
processed without the submission of a timely, complete and conforming packet. All packets shall contain a complete
affidavit, executed under penalty of perjury by an authorized individual,
certifying that the information contained in the packet is true and correct. Untimely, incomplete and non-conforming
packets will not be processed.
A. Prequalified
status will be granted upon the approval of a timely, complete and conforming
prequalification packet by the office of inspector general.
B. An untimely,
incomplete, or nonconforming packet will result in delays affecting
prequalification status and will negatively impact the prime contractor’s
ability to bid on New Mexico department of transportation projects.
(1) Obtaining
prequalified status is a condition to submitting a bid. Prime contractors submitting a new
prequalification packet or renewal prequalification packet must be approved no
later than seven calendar days before the opening of any bid.
(2) Prime
contractors submitting a bid without timely obtaining prequalified status shall
result in a determination that its bid is non-responsive and the bid shall be
rejected.
C. Subcontractors,
at any tier, must obtain prequalified status before performing any work on the
project. Work performed without prequalified
status shall be non-compensable.
D. For prime contractors and
subcontractors who are currently prequalified by the effective date of this
rule the applicant will not need to submit a new prequalification packet until
the anniversary date of their last packet.
E. For prime
contractors and subcontractors submitting packets, within five calendar days
from the receipt of a prequalification packet the office of inspector general
will provide notice of receipt of the packet.
(1) If
the packet submitted is complete and conforming then the office of inspector
general will provide written notice to the applicant of approved prequalified
status.
(2) If
the packet submitted is incomplete or does not conform to the requirements then
the office of inspector general will provide written notice to the applicant
that the packet will not be processed until the packet is complete and conforms
to the requirements.
(3) The
date of the written notice of approved prequalified status shall establish
prequalification eligibility for a period of one year. Prequalified status
shall automatically terminate if not renewed prior to the expiration date
established by the written notice of approved prequalification status.
F. Renewal packets
shall be submitted no more than 30 calendar days before the expiration date on
the document published by the office of inspector general titled prequalified
contractors and subcontractors list. Prequalified
status shall automatically terminate for the failure to submit a timely,
complete and conforming renewal packet. Prequalified
status shall be re-established upon the approval of a complete and conforming
renewal packet.
G. Appeal of the
denial of prequalification eligibility based upon the receipt of untimely,
incomplete or non-conforming packet shall be submitted in writing to the office
of inspector general with supporting documentation within seven calendar days
of the denial of prequalified status. If
the appeal is untimely the aggrieved party waives the right to appeal. The inspector general, or designee, will issue
a final written decision upholding or reversing the denial of prequalified
status within seven calendar days of the receipt of a timely appeal. The inspector general’s decision constitutes the
final action taken by the office of inspector general related to a denial of
prequalified status under this section.
H. Obtaining prequalification
status, a performance factor, or a prequalification factor rolling average does
not grant a license to do business, a right to bid or to be awarded a contract.
I. In the event a contractor
or subcontractor is suspended or debarred, its prequalification status shall
immediately and automatically terminate without further notice. In order to obtain renewed prequalification
status after a period of suspension or debarment a new complete and conforming
prequalification packet must be submitted and approved.
[18.27.5.8
NMAC - Rp, 18.27.5.8, 18.27.5.9, 18.27.5.10, 18.27.5.11, 18.27.5.12 NMAC, 1/1/2015;
A, 1/1/2019]
18.27.5.9 DEFICIENT, FALSE OR MISLEADING STATEMENTS: Any deficient, deceptive, false,
fraudulent or misleading statements in the prequalification packet or
incomplete affidavit may subject the offending party to an automatic rejection
or revocation of prequalified status, suspension, debarment proceedings or
other civil and criminal penalties under the New Mexico department of
transportation rules and may be reported to the New Mexico attorney general and
the federal highway administration for further action.
[18.27.5.9
NMAC - Rp, 18.27.5.14 NMAC, 1/1/2015]
18.27.5.10 LICENSING: Only contractors
licensed in New Mexico may perform highway construction work for the New Mexico
department of transportation. The timing
and requirements for licensure appear in the invitation for bids for the
project. All persons seeking additional
information should refer to the New Mexico CID rules and regulations and the Construction
Industries Licensing Act. Contractors
are not required to have the necessary construction industry licenses to submit
a prequalification packet.
[18.27.5.10
NMAC - Rp, 18.27.5.9 NMAC, 1/1/2015]
18.27.5.11 PREQUALIFICATION CALCULATION: The New Mexico department of transportation
will gather prime contractor performance data from each project upon project closure.
The data collected will be used to calculate
a yearly prequalification factor. The
prequalification factor rolling average will be applied to each prequalified
prime contractor to evaluate the prime contractor’s bid for department projects
as indicated in the invitation for bids.
A. The performance
factors are claims, disincentives, liquidated damages, non-conformance, safety,
and subcontractor.
(1) Pf
claim data will be documented on the compass form and will be collected from
the New Mexico department of transportation’s closed project records.
(2) Pf
disincentive data will be documented on the compass form and will be collected
from the New Mexico department of transportation’s closed project records
indicating whether disincentives were assessed on standard specification division
for surface treatment and pavements and division for quality criteria items.
(3) Pf
liquidated damages data will be documented on the compass form and will be
collected from the New Mexico department of transportation’s closed project
records indicating whether liquidated damages were assessed.
(4) Pf
non-conformance data will be documented on the compass form and will be
collected from the New Mexico department of transportation’s closed project
records indicating whether non-conformances were assessed.
(5) Pf
safety data will be the contractor’s experience modifier rating as reported on
its prequalification packet.
(6) Pf
subcontractor data will be documented on the compass form and will be collected
from the New Mexico department of transportation’s construction and civil
rights bureau records indicating findings for the failure to promptly pay subcontractors
without good cause.
B. The performance
factors are assigned percentage values within the yearly prequalification factor
calculation.
(1) The
percentage associated with claims is fifteen percent.
(2) The
percentage associated with disincentives is thirty percent.
(3) The
percentage associated with the liquidated damages is thirty percent.
(4) The
percentage associated with non-conformances is ten percent.
(5) The
percentage associated with safety is five percent.
(6) The
percentage associated with subcontractor is ten percent.
C. Pf claim or Pfc
is calculated in the following manner:
(1) Claims
that are not pursued beyond the cabinet secretary administrative remedy level
will not be included in the calculation for Pf claim.
(2) For
claims that are pursued beyond the cabinet secretary administrative remedy
level a binary system will be used to assign a value of zero or one to evaluate
claims.
(a) Claims
resolved for the value of the claim or more brought beyond the cabinet
secretary level will be assigned a value of zero.
(b) Claims
resolved for less than the value of the claim brought beyond the cabinet
secretary level will be assigned a value of one.
(3) Pf
claim is calculated by adding the number one to the outcome of the sum of the
claim value divided by the sum of closed projects.
(4) Pf
claim resulting in a value of one will be assigned a bonus value for Pf claim
equal to 0.9.
(5) Pf
claim will then be multiplied by the percentage associated with Pf claim. The
resulting value will be incorporated into Pqfyr.
D. Pf disincentive
or Pfd is calculated in the following manner:
(1) For
each closed project:
(a) Sum
paid and accepted applicable contract items.
(b) Sum
of paid and accepted applicable contract items less applicable contract
disincentives.
(c) Divide
the total of Subparagraph (a) by the total of Subparagraph (b) of Paragraph (1)
of Subsection D of this Section.
(d) If
Subparagraph (a) is equal to zero of Paragraph (1) of Subsection D of this Section
Subparagraph (c) of this Section will be assigned a value of one.
(e) If
the result of Subparagraph (c) of Paragraph (1) of Subsection D of this Section
is exactly one with paid and accepted applicable contract items Subparagraph
(c) of this Section will be assigned a value equal to 0.9.
(2) Sum
all closed projects of Subparagraph (c) of Paragraph (1) of Subsection D of
this Section in a given year and divide by the count of closed projects
resulting in Pfd.
(3) Pf
disincentive will then be multiplied by the percentage associated with Pf
disincentive. The resulting value will be incorporated into Pqfyr.
E. Pf liquidated
damages or Pfld has two separate methods of calculation one for mandatory
completion date projects and one for calendar or working day projects:
(1) For
mandatory completion date projects liquidated damages equivalence is calculated:
(a) Subtract
the mandatory completion date including any awarded time from the notice to
proceed date to equate to a whole number.
(b) Subtract
the actual completion date from the notice to proceed date to equate to a whole
number.
(c) Divide
the total of Subparagraph (b) by the total of Subparagraph (a) of Paragraph (1)
of Subsection E of this Section.
(d) A
resulting value less than or equal to one from Subparagraph (c) of Paragraph
(1) of Subsection E of this Section will be assigned a bonus value equal to
0.9.
(2) For
calendar or working day projects liquidated damages equivalence is calculated:
(a) Sum
of the total days charged.
(b) Sum
of the total days contracted.
(c) Divide
the total of Subparagraph (a) by Subparagraph (b) of Paragraph (2) of
Subsection E of this Section.
(d) A
resulting value less than or equal to one from Subparagraph (c) of Paragraph (2)
of Subsection E of this Section will be assigned a bonus value equal to 0.9.
(3) Pf
liquidated damages for a given year is the calculated from all project liquidated
damages. Pf liquidated damages is the sum of liquidated damages equivalence for
mandatory completion date, calendar or working day projects divided by the
count of closed projects resulting in Pfld.
(4) Pf
liquidated damages will then be multiplied by the percentage associated with
Pfld. The resulting value will be
incorporated into Pqfyr.
F. Pf non-conformance
or Pfn is calculated in the following manner:
(1) Sum
the number of progress payments per project.
(2) Sum
the number of progress payments without non-conformance.
(3) Divide
Paragraph (1) by Paragraph (2) of this Subsection.
(4) A
resulting value of one for Paragraph (3) of this Subsection will be assigned a
bonus value equal to 0.9.
(5) Sum
all closed projects of Paragraph (4) of this Subsection in a given year and
divide by the count of closed projects resulting in Pfn.
(6) Pf
non-conformance for a given year will then be multiplied by the percentage associated
with Pfn. The resulting value will be
incorporated into Pqfyr.
G. The performance factor
for safety or Pfs is the contractor’s experience modifier rate supplied
annually by the contractor at the time of submission of the prequalification packet.
(1) Pfs
for a given year is the numerical value of the contractor’s experience modifier
rate.
(2) If
the experience modifier is equal to or less than one the Pfs is assigned a
value of 0.9.
(3) The
experience modifier rate is multiplied by the percentage associated with Pfs.
The resulting value will be incorporated into Pqfyr.
H. Pf subcontractor
or Pfsc is calculated in the following manner:
(1) Negative
findings against the prime contractor per project will result in a value of one
per finding.
(2) Pfsc
for a given year is the sum of all negative findings in the year.
(3) Zero
findings on all closed projects within the year will receive a bonus of Pf subcontractor
equal to 0.9.
(4) The
sum of Pfsc for a given year is multiplied by the percentage associated with
Pfsc. The resulting value will be incorporated into Pqfyr.
I. The
contractor’s yearly performance factor is the sum of the individual performance
factors multiplied by their associated percentages.
J. The equation is
Pqfyr=Pfc*fifteen percent+Pfd*thirty percent+Pfld*thirty percent+Pfn*ten
percent+Pfs*five percent+Pfsc*ten percent.
K. In the absence
of data for any given year a contractor’s Pqfyr will be assigned a value of
one.
L. For joint
ventures the higher value of all joint venture applicant’s Pqfra will be used
for the modified bid amount.
M. The contractor’s
prequalification factor rolling average will be denoted as Pqfra.
(1) The
Pqfra will be calculated through the use of a rolling average covering a period
of three years. Each rolling average
year will be assigned a weighting factor and will be multiplied by the
appropriate weighting factor starting with the most recent year.
(2) The
most recent year, denoted as Pqfyr 1, will be multiplied by the weighting
factor of 0.9.
(3) The
preceding year, denoted as Pqfyr 2, will be multiplied by the weighting factor
of 0.6.
(4) The
preceding year, denoted as Pqfyr 3, will be multiplied by the weighting factor
of 0.3.
(5) The
sum of Pqfyr 1 through Pqfyr 3, is multiplied by their appropriate weighting
factors and then divided by the sum of all weighting factors to result in the
contractor’s overall Pqfra.
N. The equation for
Pqfra=(Pqfyr 1 * 0.9+Pqfyr 2 * 0.6+Pqfyr 3 *0.3)/(0.9+0.6+0.3).
O. All equations
and calculations whether interim or final will be rounded to the thousandths
place.
[18.27.5.11
NMAC - N, 1/1/2015; A, 1/1/2019]
18.27.5.12 POSTING, REVIEW AND APPLICATION OF PREQUALIFICATION
FACTOR: The following
procedures will apply to the posting, review and application of the
prequalification factor:
A. The Pqfra will
be calculated once a year on projects closed between January first and December
thirty-first of the previous year.
B. The Pqfra will
be posted on the office of inspector general list titled prequalified
contractors and subcontractors list by the second Friday in January on the
department’s website.
C. The Pqfra will
be applied to a prime contractor’s bid(s) beginning with the March bid opening
until superseded by an updated Pqfra.
D. The Pqfra will
be used to determine the modified bid amount.
E. A Pqfra may be
re-calculated and reposted at times other than the second Friday in January in
order to implement the decision of a hearing officer, a court order or a
required correction.
[18.27.5.12
NMAC - N, 1/1/2015; A, 1/1/2019]
18.27.5.13 APPEAL PROCEDURE:
In
the event of the appeal of a contractor’s prequalification factor the following
procedures shall apply:
A. Only a
contractor disputing their own prequalification factor shall have the right to
appeal their factor to the New Mexico department of transportation under this
section.
B. To be considered
an appeal must conform in timing, form and service to all requirements in this
section or the appeal shall be rejected.
C. A contractor disputing
only the misapplication of its prequalification factor to their bid shall file
the appeal according to the bidding dispute resolution procedures in the division
100-general provisions of the New Mexico department of transportation current
edition of the standard specifications for highway and bridge construction at
time of bid.
D. A contractor disputing
only the calculation of its prequalification factor shall file its appeal within
seven calendar days of the publication of their prequalification factor.
E. The appeal filed
must conform to the requirements below and contain the following information:
(1) The
appeal shall be in writing.
(2) Appeals
made by electronic mail shall not be considered.
(3) The
appeal shall clearly and concisely state the party’s right to appeal, the
grounds for appeal, the requested relief, and contain relevant laws, rules, regulations
and documents to support the appeal.
(a) Sufficient
copies of cited laws, rules, regulations, or documentary evidence shall be
included with the appeal.
(b) Supporting
documentary evidence not submitted at the time of filing the appeal shall be
submitted no later than five calendar days before the hearing.
(4) The
documents submitted in the appeal process shall not be considered confidential
and will be subject to the Inspection of Public Records Act, Sections 14-2-1 to
14-2-12 NMSA 1978 (1993, as amended through 2011).
F. Service of the
appeal shall occur as follows:
(1) A
contractor disputing its prequalification factor shall serve the appeal upon
the New Mexico department of transportation’s cabinet secretary. The contractor shall contemporaneously provide
a copy of the appeal to the office of general counsel and the office of
inspector general at the respective address for each.
(2) Service
upon the cabinet secretary must be made either in person, by certified mail
return receipt requested, or by delivery by a nationally recognized courier.
(3) Service
must be made during regular business hours.
(4) Service
made outside of regular business hours will be considered effective the next
business day.
G. 10 calendar days
after receipt of a timely and complete appeal the cabinet secretary shall
provide the following:
(1) Notice
to all parties advising the parties that an informal hearing will be convened
and designating a neutral hearing officer or designating the cabinet secretary as
the hearing officer.
(2) Within
seven calendar days of the cabinet secretary’s designation the hearing officer
will provide a notice to all parties of hearing with the date, time and
location of the hearing. The notice of
hearing will be provided no later than seven calendar days before the chosen
hearing date for the informal hearing.
H. The formal rules
of civil procedure, formal discovery processes, and the formal rules of
evidence shall not apply to the informal hearing.
(1) Any
party to the appeal may choose to have legal counsel present.
(2) The
hearing officer has the authority to determine the degree of formality of the
hearing.
(3) The
hearing officer has the authority to determine the total time allotted for the
informal hearing and how the time will be apportioned between the parties.
I. The hearing
officer shall be responsible for maintaining a record of the evidence and
proceedings.
(1) The
hearing officer will weigh the credibility of the evidence provided by both
parties.
(2) The
hearing officer may use any reliable information, no matter the source, in
arriving at a determination.
(3) If
the hearing officer uses information in the determination not provided by
either party then the hearing officer will allow a reasonable amount of time
for rebuttal from either party.
J. The hearing
officer shall issue a decision regarding the appeal within seven calendar days
of the hearing unless otherwise extended by the hearing officer in writing, no
extension shall exceed 21 calendar days from the hearing.
(1) The
hearing officer’s decision will constitute the final department action on the appeal.
(2) No
further action on the appeal may be taken by the either party if the hearing
officer’s decision is accepted by both parties.
(3) If
either party does not fully accept the hearing officer’s decision then that
party may proceed with an appeal in state district court by filing the
appropriate pleadings.
K. Record of the
appeal through the hearing officer’s decision will be maintained by the office
of inspector general for seven years after the date of the informal hearing.
L. For bidding
purposes and during the period of appeal the contractor’s previous
prequalification factor will apply.
[18.27.5.13
NMAC - N, 1/1/2015; A, 1/1/2019]
18.27.5.14 PREQUALIFICATION COMMITTEE: Members of the prequalification committee
will be designated by the cabinet secretary of the New Mexico department of
transportation and shall meet annually to review the prequalification process.
Any information reported by a prime contractor or subcontractor during the
prequalification process may be reviewed by the prequalification committee to
determine responsibility.
[18.27.5.14
NMAC - N, 01-01-15]
18.27.5.15 PREQUALIFICATION FOR CONSOLIDATED CORPORATIONS, MERGED
CORPORATIONS, AND JOINT VENTURES: The following
prequalification packet procedure and Pqfra will apply to consolidated
corporations, merged corporations and joint ventures:
A. For a
consolidated corporation pursuant to Subsection A of 54-1A-303 NMSA 1978, or a
similar statutory provision, the new corporation must be prequalified no later
than seven calendar days before the opening of any bid.
B. For a merged
corporation pursuant to Subsection A of 54-1A-303 NMSA 1978, or a similar
statutory provision, the surviving corporation must be prequalified no later
than seven calendar days before the opening of any bid. The Pqfra score of the surviving corporation
will be the highest Pqfra of the individual corporations who merged and will be
used for the modified bid amount.
C. Each prime
contractor participating in the joint venture must be individually prequalified
seven calendar days before bid opening to join forces as a joint venture for
bidding and performing work related to a single project. The joint venture itself need not prequalify.
(1) The
joint venture shall file with the office of inspector general at least seven
calendar days before the opening of any bid a completed statement of joint
venture form. The most current version
of the statement of joint venture form must be obtained from the New Mexico
department of transportation website.
(2) For
joint ventures the higher value of all joint venture applicant’s Pqfra will be
used for the modified bid amount.
(3) Each
prime contractor participating in the joint venture will receive a compass form
for the project to be used in calculating the prime contractor’s individual
prequalification factor.
[18.27.5.15
NMAC - Rp, 18.27.5.15, 1/1/2015; A, 1/1/2019]
18.27.5.16 ADOPTION OF THE NEW MEXICO STATE DEPARTMENT OF
TRANSPORTATION CURRENT EDITION OF THE STANDARD SPECIFICATIONS FOR HIGHWAY AND
BRIDGE CONSTRUCTION: This rule adopts
by reference the current edition of the New
Mexico state department of transportation standard specifications for highway
and bridge construction, as amended by this rule.
[18.27.5.17
NMAC - N, 1/1/2015]
HISTORY OF 18.27.5 NMAC:
Pre-NMAC History: None
History of the Repealed Material:
18
NMAC 27.5, Highway Construction General Provisions-Contractor
Prequalifications, filed 11/13/1998.
This was a temporary rule expiring 120 days from effective date of
11/30/1998.
18.27.5
NMAC, Contractor Prequalification Rule, (filed 12/07/2000) repealed and
replaced by 18.27.5 NMAC, Contractor Prequalification Rule, effective 01/01/2015.